Parts used

1 3/4 DOM tubing.
1"-14 reverse thread heim joints
4 link brackets from chassis engineering front and back
1"-14 treaded rod end studs
bushings from a Jeep
3/4x6 bolts
high missalignment spacers TMR

I got a good deal on some 1 3/4 DOM, so I based this build off of that. Little did I know at the time how pricey and difficult it would be to aquire all the pieces I needed. This thread is mainly geared around the control arm build. All the rest is in the western region, under Crockett checking in.

First order of business was to mount the rodends to all mounting points and position the axle in the center line and measure the length of the bars needed. Cut to length and check positions.

Next step was to bevel edges at a sixty degree angle. To aid in a greater surface area for the weld bead to grab to. After that drill holes for a rosette weld. The rosette weld is there for safety sake.

Next I gave the rod end bung an 1/8 gap between it and and the bar. Tack welded in four positions and compared to the other matching bar prior to final weld.

Ran a first bead making sure to melt the bung to the bar. Looked good to me.

Then ran the final bead to build slightly higher then the surface. To aid in grinding smooth later. After weld beads cooled I did the rosette weld.

I got the beat up makita grinder out and ground the best I could with out going to deep or deep at all.

After grinding I used a sanding disk and air grinder medium cut. All that really did was shine things up. Unhappy with that I switched to my belt sander with a used 80 grit. It worked pretty good at getting the scratches out. I then switched to a 2 inch sanding disk I believe it was an 80 grit. That worked out a whole lot better.

Once all the grinding and sanding was done. I could install the rod ends. With alittle anti seize on the threads they turned in nicely to a point where they started to get snug. Probibly from the welding. So in the vice with ya! I used a crow bar to work them back and forth to loosen their grip. It worked and was able to turn by hand in the end.

Once complete. I mounted them to the chassis. I thought this part of the build came out nicely and wanted to share. As well as inform. Thanks for viewing and have a great day.11759117561176011779117801178111782117831178411786117871178811789117901179111792
rbeck204
Posts: 117
Joined: July 19, 2011, 11:14 pm
Location: Moving to Houston, TX
United States of America

Re: 4 Link control arm build.

Post by rbeck204 »

Really nice work. Can't wait to see the finished product
Rich
61 T Bird Convertible
1953 Ford Customline 2 door
User avatar
milldinaire
Posts: 125
Joined: December 28, 2012, 7:50 pm
Location: Crockett, CA
United States of America

Re: 4 Link control arm build.

Post by milldinaire »

Thanks Rich. Me too. Still gots lots of work to do in the bed. I guess now I finally get to open up my tubs and finangle those together. Happy good times for sure. By the by I got your message and the eagle will return the golden egg minus some silver. Thanks man.